King Edwards School

161.95kWp

Bauder BioSolar System

Overview

PV Plus delivered a large-scale solar PV project across three buildings at King Edward VI School, Southampton, totalling 162kWp. The installation supports the school’s sustainability strategy and reduces operational energy costs while integrating across both pitched and flat roof areas.

161.95kWp

System Size

153.85MWh

Yearly Generation

35.85 Tonnes

Carbon saving per annum

The Challenge
The project required three separate solar systems, each with its own MPAN, spread across different roof types: Bauder flat roof, pitched Renusol, and sports hall roofing. Close coordination was needed to manage multiple inverters, ensure DNO compliance, and deliver within a live school environment.

Our Solution
PV Plus installed a total of 395 JA Solar 410W panels (161.95kWp) configured as follows:

  • Central Building – 152 panels on Bauder flat roof, linked to a 66.6kW SolarEdge inverter

  • Right / Sports Hall – 142 panels (24 pitched + 123 flat roof), linked to a 50kW SolarEdge inverter

  • Left Science Block – 96 panels on pitched roof with Renusol mounts, linked to a 30kW SolarEdge inverter

Each system was designed with SolarEdge optimisation for maximum performance and to support the school’s long-term energy strategy.

The Result
The combined systems will generate around 154 MWh of renewable energy annually, saving approximately 36 tonnes of CO₂ per year. This reduces the school’s grid reliance and supports its wider Net Zero ambitions.

Why PV Plus
PV Plus brings extensive experience in education projects, ensuring installations are delivered safely, on time, and with minimal disruption to staff and students. Our ability to coordinate complex, multi-roof and multi-inverter projects makes us the trusted partner for large institutions like King Edward VI School.

Client

King Edwards School

Installation size

161.95kWp

Panel Type

SolarWatt

Mounting type

Bauder BioSolar

Inverter type

SolarEdge