PV Plus delivered the electrical installation and commissioning for a ~490 kWp PV system at the New Milton Data Centre, wiring and fitting 1,195 modules on a Bauder flat roof (Revision 4). The project supports the client’s energy resilience goals while reducing operational carbon for a 24/7 load profile.

489.95kWp

System Size

465.45MWh

Yearly Generation

108.45 Tonnes

Carbon saving per annum

The Challenge

Data centres demand absolute reliability, tight coordination, and clean cable management. The roof build-up required compatibility with Bauder details and strict pathways for containment to avoid clashes with plant, roof outlets, and fall protection.

Our Solution

Working to Ithaca’s supply package, PV Plus completed the installation and terminations for:

  • 1,195 x SolarWatt 410 W panels (total 489.95 kWp)

  • Bauder-compatible mounting system (Ithaca supplied)

  • 4 x Solis PRO 100 kW three-phase inverters (each rated at 167.1 A 3-phase as specified)

  • DC strings, DC isolators, AC switchgear, containment, testing, and commissioning

The Result

The system is expected to generate ~465 MWh/year, cutting approximately ~108 tonnes of CO₂ annually. The array provides steady daytime offset for the facility’s continuous electrical demand, reducing grid import and long-term operating costs.

Why PV Plus

We’re a trusted delivery partner for complex commercial roofs, combining clean installation standards with seamless coordination alongside roofing contractors and suppliers. For mission-critical sites like data centres, our team delivers safe, compliant, and tidy installs that perform.

Client

Ithaca Roofing

Installation size

489.95kWp

Sector

Commercial

Panel Type

SolarWatt

Mounting type

Bauder Flat

Inverter type

Solis

Partners that we worked with on this project